How long does a bathroom renovation take? Complete timeline per phase
Direct answer: A bathroom renovation takes on average 2 to 4 weeks for a standard project (5-7m², new pipes, no structural work). --- Cosmetic refresh ---: 1-2 weeks. Full strip + custom work: 5-7 weeks. Plus 1-2 weeks in advance for planning and orders.
--- The most frequently asked question we get, after "what does it cost", is "how long will it take?". The honest answer: it depends. But in this guide we give you the realistic lead times per type of renovation and per phase, based on 187+ projects we carried out in 2024-2025. ---
Timeline by Renovation Type
| Type | Lead time | Ready. Please paste the Dutch HTML text you want translated to English. |
|---|---|---|
| Cosmetic refresh | 5-10 business days | New tiles over existing, replace sanitary ware, keep pipework |
| Standard renovation | 3-4 weeks | New pipes, 1-2 relocations, shower tray → walk-in shower |
| Full strip + rebuild | 5-7 weeks | Complete strip-out, new structure, custom sanitary fittings, underfloor heating |
| Premium custom work | 7-10 weeks | Freestanding bath, natural stone, designer taps, custom-made furniture |
Full timeline: standard renovation (3-4 weeks)
Week 0 — Preparation (before the works begin)
- Dag 1-2: Offerte + definitieve materiaalkeuze (tegel showroom, sanitair, kranen)
- Day 3-5: Order sanitaryware — delivery time 5-10 business days for common brands, 2-4 weeks for custom work
- Day 6-7: Planning, permit check (usually not required for renovation, but required for structural changes)
- Day 8-10: Arrange workers (if you are not working with your own contractor)
--- Week 1 — Demolition + Piping ---
- Day 1-2: Demolition of the old bathroom. Container, rubble removal. Dust and noise — don't be alarmed.
- Day 3-5: Run new pipes (hot, cold, drain). Relocate pipes if the sanitary fixtures will be on a different wall.
- Day 5-7: Electricity: new cables for lighting, sockets, ventilation.
--- Week 2 — Preparatory work + waterproofing ---
- Day 8-9: Screed (levelling layer) on floor. Thickness 3-5 cm. Drying time: 3-5 days.
- Day 10-11: Apply waterproofing (liquid membrane). Two coats, 24h drying time between.
- Day 12-13: Inspect wall substrate and level if necessary.
--- Week 3-4 — Tiling + sanitary ---
- Day 14-18: Tiling. Wall first, then floor. This is the longest phase and cannot be shortened.
- Day 19-20: Grouting + curing (24-48h).
- Day 21-22: Install sanitary fixtures: shower, bath, toilet, washbasin, taps.
- Day 23-24: Silicone sealing, final assembly, electrical finishing (lighting, switches).
- Day 25-28: Handover + small touch-ups + handover documents.
After week 4 — Ready for use
Usually, you can start using the bathroom on day 28-30. The screed must cure for 4 weeks before heavy loading, but light use (showering) is possible sooner.
What can extend the schedule?
- ⏰ Sanitaryware not in stock — typically 2-4 weeks delay for custom work. Order 6 weeks in advance.
- ⏰ Asbestos or hidden problems — homes built before 1990 may contain asbestos in tile adhesive or screed. First asbestos removal (€1.500-€3.500, +1 week).
- ⏰ Hidden pipes — old lead pipes or concrete screed that needs to be stripped.
- ⏰ Waiting for materials — special tiles or taps can have a delivery time of 4-6 weeks.
- ⏰ Moisture problems discovered during works — if we open the wall and find mould, this must be treated first (€500-€2,000 extra).
- ⏰ Changes during the works — “actually, we’d still like a different tap” midway through week 2. Adds 2–3 days of delay.
What can shorten the schedule?
- ✅ Choose sanitary fixtures that are in stock (not custom-made). You save 2-4 weeks delivery time.
- ✅ Order materials 6 weeks before the start, not 2 weeks.
- ✅ Have the electrician and plumber work at the same time in week 1 (instead of sequentially). Saves 2–3 days.
- ✅ Choose fast-drying screed (dries in 24h instead of 5 days). Costs 2-3x more material, saves 4 days.
- ✅ Work with a contractor with a fixed team (no subcontractors who skip days).
--- Frequently asked questions about lead time ---
How long does a bathroom renovation take on average?
Average 2-4 weeks for a standard renovation. Cosmetic: 1-2 weeks. Full strip + custom work: 5-7 weeks. Plus 1-2 weeks in advance for planning and ordering.
Can I stay in my home during the renovation?
Yes, usually. Provided you still have a second bathroom or shower, and you accept that the workers walk through your home. Otherwise you can opt for staying elsewhere for 1-2 weeks.
What is the drying time for screed and waterproofing?
Screed: 3-5 days (1 cm/week drying time). Waterproofing: 24-48h between two coats. Fast-drying screed is available but costs 2-3x more.
What is the longest phase of a bathroom renovation?
Tiling + curing: 1-2 weeks, including grouting, curing and sealing. This cannot be shortened without loss of quality.
Would you like a custom schedule?
Request a free quote + planning. We visit you for a survey and discuss the possibilities.
Request your quote + scheduleOf bel direct: 0485 44 55 12