← Back to homeπŸ“ž Call 0485 44 55 12

How long does a bathroom renovation take? Complete timeline per phase

Direct answer: A bathroom renovation takes on average 2 to 4 weeks for a standard project (5-7mΒ², new pipes, no structural work). Cosmetic refresh: 1-2 weeks. Full strip + custom work: 5-7 weeks. Plus 1-2 weeks in advance for planning and orders.

Plumber installing bathroom pipes during renovation, with walls being prepared for waterproofing and tiling.

The most frequently asked question we get, after "what does it cost", is "how long will it take?". The honest answer: it depends. But in this guide we give you the realistic lead times per type of renovation and per phase, based on 187+ projects we carried out in 2024-2025.

Timeline by Renovation Type

TypeLead timeExample
Cosmetic refresh5-10 business daysNew tiles over existing, replace sanitary ware, keep pipework
Standard renovation3-4 weeksNew pipes, 1-2 relocations, shower tray β†’ walk-in shower
Full strip + rebuild5-7 weeksComplete strip-out, new structure, custom sanitary fittings, underfloor heating
Premium custom work7-10 weeksFreestanding bath, natural stone, designer taps, custom-made furniture

Full timeline: standard renovation (3-4 weeks)

Week 0 β€” Preparation (before the works begin)

  1. Day 1-2: Quote + final choice of materials (tile showroom, sanitary ware, taps)
  2. Day 3-5: Order sanitaryware β€” delivery time 5-10 business days for common brands, 2-4 weeks for custom work
  3. Day 6-7: Planning, permit check (usually not required for renovation, but required for structural changes)
  4. Day 8-10: Arrange workers (if you are not working with your own contractor)

Week 1 β€” Demolition + Piping

Week 2 β€” Preparatory work + waterproofing

Week 3-4 β€” Tiling + sanitary

After week 4 β€” Ready for use

Usually, you can start using the bathroom on day 28-30. The screed must cure for 4 weeks before heavy loading, but light use (showering) is possible sooner.

What can extend the schedule?

  1. ⏰ Sanitaryware not in stock β€” typically 2-4 weeks delay for custom work. Order 6 weeks in advance.
  2. ⏰ Asbestos or hidden problems β€” homes built before 1990 may contain asbestos in tile adhesive or screed. First asbestos removal (€1.500-€3.500, +1 week).
  3. ⏰ Hidden pipes β€” old lead pipes or concrete screed that needs to be stripped.
  4. ⏰ Waiting for materials β€” special tiles or taps can have a delivery time of 4-6 weeks.
  5. ⏰ Moisture problems discovered during works β€” if we open the wall and find mould, this must be treated first (€500-€2,000 extra).
  6. ⏰ Changes during the works β€” β€œactually, we’d still like a different tap” midway through week 2. Adds 2–3 days of delay.

What can shorten the schedule?

Frequently asked questions about lead time

How long does a bathroom renovation take on average?

Average 2-4 weeks for a standard renovation. Cosmetic: 1-2 weeks. Full strip + custom work: 5-7 weeks. Plus 1-2 weeks in advance for planning and ordering.

Can I stay in my home during the renovation?

Yes, usually. Provided you still have a second bathroom or shower, and you accept that the workers walk through your home. Otherwise you can opt for staying elsewhere for 1-2 weeks.

What is the drying time for screed and waterproofing?

Screed: 3-5 days (1 cm/week drying time). Waterproofing: 24-48h between two coats. Fast-drying screed is available but costs 2-3x more.

What is the longest phase of a bathroom renovation?

Tiling + curing: 1-2 weeks, including grouting, curing and sealing. This cannot be shortened without loss of quality.

Would you like a custom schedule?

Request a free quote + planning. We visit you for a survey and discuss the possibilities.

Request your quote + schedule

Or call directly: 0485 44 55 12