← Back to homeπŸ“ž Bel 0485 44 55 12

How long does a bathroom renovation take? Complete timeline per phase

Direct answer: A bathroom renovation takes on average 2 to 4 weeks for a standard project (5-7mΒ², new pipes, no structural work). Cosmetic refresh: 1-2 weeks. Full strip + custom work: 5-7 weeks. Plus 1-2 weeks in advance for planning and orders.

The most frequently asked question we get, after "what does it cost", is "how long will it take?". The honest answer: it depends. But in this guide we give you the realistic lead times per type of renovation and per phase, based on 187+ projects we carried out in 2024-2025.

Timeline by Renovation Type

TypeLead timeExample
Cosmetic refresh5-10 business daysNew tiles over existing, replace sanitary ware, keep pipework
Standard renovation3-4 weeksNew pipes, 1-2 relocations, shower tray β†’ walk-in shower
Full strip + rebuild5-7 weeksComplete strip-out, new structure, custom sanitary fittings, underfloor heating
Premium custom work7-10 weeksFreestanding bath, natural stone, designer taps, custom-made furniture

Full timeline: standard renovation (3-4 weeks)

Week 0 β€” Preparation (before the works begin)

  1. Day 1-2: Quote + final choice of materials (tile showroom, sanitary ware, taps)
  2. Day 3-5: Order sanitaryware β€” delivery time 5-10 business days for common brands, 2-4 weeks for custom work
  3. Day 6-7: Planning, permit check (usually not required for renovation, but required for structural changes)
  4. Day 8-10: Arrange workers (if you are not working with your own contractor)

Week 1 β€” Demolition + Piping

Week 2 β€” Preparatory work + waterproofing

Week 3-4 β€” Tiling + sanitary

After week 4 β€” Ready for use

Usually, you can start using the bathroom on day 28-30. The screed must cure for 4 weeks before heavy loading, but light use (showering) is possible sooner.

What can extend the schedule?

  1. ⏰ Sanitaryware not in stock β€” typically 2-4 weeks delay for custom work. Order 6 weeks in advance.
  2. ⏰ Asbestos or hidden problems β€” homes built before 1990 may contain asbestos in tile adhesive or screed. First asbestos removal (€1.500-€3.500, +1 week).
  3. ⏰ Hidden pipes β€” old lead pipes or concrete screed that needs to be stripped.
  4. ⏰ Waiting for materials β€” special tiles or taps can have a delivery time of 4-6 weeks.
  5. ⏰ Moisture problems discovered during works β€” if we open the wall and find mould, this must be treated first (€500-€2,000 extra).
  6. ⏰ Changes during the works β€” β€œactually, we’d still like a different tap” midway through week 2. Adds 2–3 days of delay.

What can shorten the schedule?

Frequently asked questions about lead time

How long does a bathroom renovation take on average?

Average 2-4 weeks for a standard renovation. Cosmetic: 1-2 weeks. Full strip + custom work: 5-7 weeks. Plus 1-2 weeks in advance for planning and ordering.

Can I stay in my home during the renovation?

Yes, usually. Provided you still have a second bathroom or shower, and you accept that the workers walk through your home. Otherwise you can opt for staying elsewhere for 1-2 weeks.

What is the drying time for screed and waterproofing?

Screed: 3-5 days (1 cm/week drying time). Waterproofing: 24-48h between two coats. Fast-drying screed is available but costs 2-3x more.

What is the longest phase of a bathroom renovation?

Tiling + curing: 1-2 weeks, including grouting, curing and sealing. This cannot be shortened without loss of quality.

Would you like a custom schedule?

Request a free quote + planning. We visit you for a survey and discuss the possibilities.

Request your quote + schedule

Or call directly: 0485 44 55 12